May 13, 2024

Report Wire

News at Another Perspective

SC notes settlement, closes healing plea of GUVNL towards Adani Power for termination of PPA

2 min read

The Supreme Court on Tuesday took notice of the settlement arrived at between Adani Power (Mundra) Ltd and the Gujarat Urja Vikas Nigam Ltd (GUVNL) and closed the healing plea of the state PSU difficult the apex court docket’s 2019 verdict upholding the personal agency’s termination of an influence buy settlement (PPA).
A five-judge Constitution bench headed by Chief Justice N V Ramana was instructed by Attorney General Okay Okay Venugopal, showing for GUVNL, {that a} settlement has been arrived at between the state PSU and Adani Power (Mundra) Ltd on January 3.
The prime regulation officer stated that in view of the settlement, the healing plea be closed and the decision could also be modified accordingly.
The bench, which additionally comprised Justices U U Lalit, D Y Chandrachud, B R Gavai and Surya Kant, stated it could shut the case by recording that each the events will likely be ruled by the settlement settlement.

The counsel for Adani Power supported the submission of Venugopal and stated that the personal agency would resume supplying 2000 MW electrical energy to GUVNL as per the settlement deed.
In a major growth on September 17, final yr, the bench had determined to listen to in an open court docket the GUVNL’s healing petition which, as per business estimates, was to pay practically Rs 11,00 crore compensation to Adani Power.
A 3-judge bench in July 2019 had held that the discover of termination of a PPA by the Adani Power to GUVNL in 2009 was authorized and legitimate. It had ordered the Central Electricity Regulatory Commission (CERC) to find out compensatory tariff for the facility provided by Adani Power to the state PSU.
The verdict had stated that the court docket ought to give impact to the “plain, literal and grammatical” which means of the clauses utilized in a contract.
Adani Power (Mundra) Ltd had signed a PPA with GUVNL in 2007 to provide 1,000 MW energy from its undertaking positioned in Korba, Chhattisgarh.
Adani terminated the pact citing non-coal provide by Gujarat Mineral Development Corporation, claiming that the provision of electrical energy was conditional to coal provide.

The PPA termination discover was challenged by the GUVNL earlier than the Gujarat Electricity Regulatory Commission which had held the termination as unlawful.
The prime court docket had, nonetheless, reversed the findings.