Overruling own decisions, Baghel govt spares Tatas Rs 200 crore penalty

2 min read

VERRULING THE decisions of two IAS officers who were successive CEOs of the key nodal agency for a Rs 3,057-crore rural broadband project, the Bhupesh Baghel-led Congress government in Chhattisgarh decided not to deduct Rs 200 crore in penalties it had imposed on Tata Projects Ltd for twice not meeting its deadline.

This penalty was as per terms of the agreement between the company and the state and its imposition was a decision ratified by a Chief Secretary-led committee, records investigated by The Indian Express have found.

That’s not all — the state government also refunded a Rs 28.79-crore penalty already levied, despite having granted Tata Projects an extension of timeline twice in two years.

Awarded to the company in July 2018, the BharatNet Chhattisgarh project was originally scheduled to be completed in a year. It involves laying an optical fibre network covering 32,466 km, linking 85 blocks and 5,987 gram panchayats across 27 districts in the state.

The lighting up of gram panchayats in Chhattisgarh with internet is part of the nation-wide BharatNet project, one of the flagships under Prime Minister Narendra Modi’s Digital India plan, and aims to connect 2.5 lakh villages.

As on September 25, 2020, Tata Projects could ensure broadband-ready infrastructure in only 1,394 gram panchayats (24 per cent of the target). A detailed questionnaire mailed to Tata Projects Ltd on October 26 did not elicit a response.

Under Sameer Vishnoi, appointed on January 23 as its CEO, the Chhattisgarh Infotech Promotion Society (ChIPS), a nodal agency of the state tasked with monitoring the project, set aside the decisions of its two past CEOs – Alex Paul Menon and KC Devasenapathi, both of whom had invoked the penalty on Tata Projects for not adhering to timelines mutually agreed upon.

But these decisions were set aside by Vishnoi. When contacted, he admitted not much work had been done when he joined in January this year. “The work picked up only in the past six months. We started with only 33 gram panchayats in February, and now within a fortnight, we will inaugurate 1,200-1,500 villages,” he said.